Drivers say they are fed up with cones along the north Beltway and want to know when the work will finally be over.  Traffic8 called up the County and got answers, in “What’s Driving You Crazy?” 

Construction along the north Beltway was extended an additional 273 days, so crews can build the Revere Street interchange.  Work is set to finish up in late October.  

Upcoming projects include the Grand Montecito Parkway bridge.  The northern I-15 interchange will be built by NDOT.

Eventually, the Losee Road, Pecos Road and Lamb Boulevard intersections will be turned into interchanges, but Clark County has no estimate on when those will be constructed at this time.